Day 660 - "Go" Decision For Half Data Migration

This situation and the pressure people is getting to make things fast it's totally unbelievable. This has lead management into splitting the data migration by the next two weekends. Thus, the next weekend it will migrate customers, insurance claims and invoices. But only if they are not involved in some kind of accident, otherwise it's migration will happen in the other weekend.

This will allow the integration test teams to perform preliminary validations and I also believe it will be great because I know that the entire data migration does not integrate into GIS during a single weekend with the current AS/400 system configuration.

Meanwhile, the software patches continues to give us problems.

Day 658 - Next Qualification Migration In Risk

According to planing, in the next weekend a new data migration should occur in the qualification environment. But unfortunately there's so many problems and change requests happening that the mapping is very unstable within a few days from the beginning of the data migration.

This next weekend data migration is in risk, and this is critical for the entire project, since the data migration is in the project critical path.

Management still doesn't know if it's a "go" or a "no go", that decision will be taken late this week.

Day 655 - Under Pressure

This past week the team has been reinforced with one extra person. This was critical because we had 4% of change requests during this past 5 week. He have implemented and tested 146 change requests, including new mapping tables and claim mappings that should be stable for weeks now.

This kind of instability is making the entire team under great pressure beacause within one week, a new data migration will be performed to qualification environment.

Tuesday, January 11, 2011

Day 651 - Distinct Views of the Same Situation

Management and me disagree when it comes to the current status of the data migration project.
Management seems happy with it and I'm concerned with the quantity of change requests we're getting when we're so near the next big data migration.
After that we'll have only one month before the beginning of the simulations and I'm not happy because I already know things will change a lot again.

I'm very concerned with this kind of undesired activity since it may be a no-go factor.
Management has not taken my opinion too seriously and has assured its own team things are ok.

Day 647 - New Patch

It's unbelievable the quantity of patches GIS has already received in order to increase its functionality and to fix the bugs previous patches have introduced!
I've lost two mornings working with the functional team in the account module just to find out that we were on a witch chase.
The problem was on GIS and we have just been informed that the new patch fixes the errors we were getting. The problem is that these errors only appeared after a previous software installation the week before.

Day 643 - The Begining of Massive Changes

New year's gone and we're starting a massive change set on things that should be closed and stable.
Change requests have already started, but management asked me to increase the team since there will be a lot of change requests very soon and they need to be ready and the mapping must be stabilized for the next big data migration into the Q&A environment.
I have some concerns with this kind of activity when we're just two weeks away from the next big test.