This situation and the pressure people is getting to make things fast it's totally unbelievable. This has lead management into splitting the data migration by the next two weekends. Thus, the next weekend it will migrate customers, insurance claims and invoices. But only if they are not involved in some kind of accident, otherwise it's migration will happen in the other weekend.
This will allow the integration test teams to perform preliminary validations and I also believe it will be great because I know that the entire data migration does not integrate into GIS during a single weekend with the current AS/400 system configuration.
Meanwhile, the software patches continues to give us problems.
Saturday, January 22, 2011
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment