The project has been officially kicked off.
There was the traditional meeting where all teams where present and an overview of the project was presented. All teams involved have previous data migration experience, which is good.
The project should be completed around mid October, but I felt that management confidence to comply with the date is not very high. This is not a bad signal as one might think, since management showed that it is aware of some real difficulties. Those difficulties may become technical challenges and may delay the project.
Nevertheless, I do believe that the original due date can be achieved.
There will be two phases. The first phase, the current one, will use a small entity subset in order to test the performance of the ETL and to tune the process.
The second phase will be the continuity of the previous phase, but now including all applications and entities.
The project itself consists of migrating the current insurance application, running on OS/390 mainframe, into the new system, the GIS Non-Life, running on AS/400, all using DB2, SAM and VSAM.
There are some other satellite applications running on SQL Server 2005 on Windows.
The ETL tool will be Data Fusion and it will run on AS/400 under the Qshell.
The ETL process will be implemented in a slightly different way from the usual scenario. Usually the data is extracted from the source database and loaded into the target database. This is not the case in this project.
Eventually, the data will be loaded into the final target database, but there's an intermediate step. The ETL process performed by Data Fusion will deliver the data on flat files that will be later consumed by the GIS loader. The GIS loader will validate and load the data into the final database.
Since our (ETL team) experience tells us that performance on AS/400 may be a problem during the ETL process, there was some discussion over the performance tests to be performed during phase one.
If the performance becomes an issue, the data migration may have to be incremental, instead of one-shot. This will be a problem because the source team cannot identify which data has been changed and needs to be migrated again to refresh the target system. One challenge that has been given to us, is to think in a fast way to identify if a record has changed and needs to be migrated again, just in case of a B plan is required.
Wednesday, April 1, 2009
Day 1 - Kick off