Day 287 - Project Due Date Postponed

The project due date has been postponed almost two months. The D-Day date is now June 1st.
This happened because sub-projects related with the target system, such as testing, were delaying.
This is actually the first time I'm on a data migration project were, once set, the official D-Day had been postponed.
As far as I know, the data migration itself was one of the few projects that was on schedule.

The data migration will have to comply with this date and this probably mean that for one month we will have one extra resource. This is still unclear and thus the resize of the team is still under analysis.